Scheduled Custom Script Uses Wrong Script?

I created a Custom Script doing a Smart Update of the Documents folder only, tested it and it worked fine. I then Scheduled it to run at a specified time. When it ran, the script it used was the Standard Scripts/BackUp - all files, and not the Custom Script I thought I had scheduled to run. When I looked at the log, it called for the BackUp - all files script. Why is the wrong script being used? Also, although the custom script ran at the correct time, when I looked at the schedule, it said 9:30 pm, even though it ran at 12:00, the time I wanted. Is the 9:30 setting a default that appears even when the scheduled time is something else?