PDA

View Full Version : Scheduled Back-ups when computer switched off


Bob Kerr
11-07-2006, 01:44 PM
Hi,

I'm brand new to SuperDuper but have just registered and plan to use it for (weekday) daily scheduled back-ups. I had a look in FAQs but couldn't find the answer. Sorry if the question has been covered elsewhere.

Basically what happens if my Mac is switched off for the day when a back-up is scheduled?

dnanian
11-07-2006, 02:41 PM
The backup is skipped, Bob.

Bob Kerr
11-07-2006, 02:58 PM
But it continues with the schedule the next time (scheduled time) the Mac is switched on – no harm done?

dnanian
11-07-2006, 02:58 PM
That's right: it'll just wait until the next time comes around. No harm done.

Bob Kerr
11-07-2006, 05:06 PM
Thank you.